Application Information:

To top of page

License Renewal Review Schedule:

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 08/30/10 08/30/10
Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10
Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10
Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10
Public Meeting - license renewal process and environmental scoping 11/04/10 11/04/10
Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10
Environmental scoping periods ends 12/27/10 12/27/10
Audit - scoping and screening methodology 01/24/11 01/24/11
Audit - aging management programs (AMPs) 02/14/11 02/14/11
Audit - environmental 03/07/11 03/07/11
Inspection - scoping, screening, and AMPs 04/2011 04/25/11
Environmental Requests for Additional Information (RAIs) - Issued 04/08/11 02/23/11
Safety RAIs - Issued 04/29/11 04/29/11
Environmental RAIs - Response Received 05/13/11 03/23/11
Safety RAI - Responses Received 05/30/11 05/30/11
Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12
ACRS subcommittee meeting on SER with open item(s) 09/19/12 09/19/12
Issue SER 09/2013 09/03/13
Issue draft supplemental environmental impact statement (SEIS) 02/2014 02/26/14
Public Meeting - draft SEIS 03/2014 03/25/14
End of comment period for the draft SEIS 04/2014 04/21/14
Issue final SEIS 04/2015 04/24/15
Issue Supplemental SER 08/2015 08/10/15
ACRS second subcommittee meeting on SER 09/23/15  
ACRS full committee meeting on SER 11/05/15  
Decision - Director, Office of Nuclear Reactor Regulation 12/2015 12/08/15

Note: The Davis-Besse review schedule was revised as described in the letter below:

To top of page

Safety Evaluation Report

The NRC staff reviewed the Davis-Besse Nuclear Power Station license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on July 31, 2012, as "Safety Evaluation Report with Open Items Related to the License Renewal of Davis-Besse Nuclear Power Station."

Subsequently, on September 3, 2013, the document "Safety Evaluation Report Related to the License Renewal of Davis-Besse Nuclear Power Station" was issued. On August 10, 2015, the staff issued Supplement 1 to "Safety Evaluation Report Related to the License Renewal of Davis-Besse Nuclear Power Station."

In April 2016, the staff published the final "Safety Evaluation Report Related to the License Renewal of Davis-Besse Nuclear Power Station" as NUREG-2193 Volume 1 and NUREG-2193 Volume 2.

In April 2016, the staff published Supplement 1 to the final "Safety Evaluation Report Related to the License Renewal of Davis-Besse Nuclear Power Station" as NUREG-2193 Supplement 1.

To top of page

Environmental Impact Statement

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Unit 1 (NUREG-1437, Supplement 52) Final Report," was published in April 2015. This supplement documents the NRC staff's review of the environmental issues at Davis-Besse Nuclear Power Station, Unit 1 regarding the FirstEnergy Nuclear Operating Company application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the NRC staff's preliminary recommendation regarding the proposed action.

To top of page

Public Involvement

The public was encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
03/25/2014

Meeting to discuss the preliminary results of the environmental review for Davis-Besse Nuclear Power Station, Unit 1

11/04/2010

Meeting to discuss the license renewal process and environmental scoping for Davis-Besse Nuclear Power Station, Unit 1

To top of page

Section Navigation

Page Last Reviewed/Updated Friday, August 28, 2020