Browns Ferry Nuclear Plant, Units 1, 2, and 3 – Subsequent License Renewal Application

Image of Browns Ferry Nuclear Plant, Units 1, 2, and 3 – Subsequent License Renewal Application

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

(To top of page)

License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) January 2023 January 19, 2024
Publish Federal Register Notice (FRN) – SLRA Availability February 2023 February 8, 2024
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing March 2024 March 21, 2024
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping April 2024 April 3, 2024
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping April 2024  
Environmental Scoping Period Ends May 2024 May 3, 2024
Deadline for Filing Hearing Requests and Petitions for Intervention May 2024 May 20, 2024
Issue Safety Evaluation Report April 2025  
Issue Draft Supplemental Environmental Impact Statement (DSEIS) May 2025  
Public Meeting – Draft SEIS Meeting, If Needed June 2025  
End of DSEIS Comment Period June 2025  
Advisory Committee on Reactor Safeguards Full Committee Meeting June 2025  
Issue Final SEIS November 2025  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS November 2025  
Decision – Director, Office of Nuclear Reactor Regulation January 2026  

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date Description
04/11/2024 Meeting to discuss the license renewal process and environmental scoping for Browns Ferry Nuclear Plant, Units 1, 2, and 3
04/18/2024 Meeting to discuss the license renewal process and environmental scoping for Browns Ferry Nuclear Plant, Units 1, 2, and 3

(To top of page)

Project Managers

Browns Ferry Nuclear Plant, Units 1, 2, and 3 PMs
License Renewal (Safety) Jessica Hammock
License Renewal (Environmental) Jessica Umana
Lead Power Plant Kimberly Green